Engine Operation 3.1 Commissioning
3.1.3 Other Preparations
Check battery and cable connectors,
see 6.7.1.
Transport hooks
Remove if fitted (see 6.7.3)
Trial run
After engine has been prepared, let it run for
about 10 minutes without being loaded.
During and after trial run
- Check engine for leaks.
After engine has been turned off
- Check oil level,
see 6.1.2.
Top up with oil, if necessary,
see 3.1.1.
- Retension V-belt,
see 6.5).
3.1.4 Additional Maintenance Work
When commissioning new and reconditioned en-
gines, the following additional maintenance work
must be carried out:
Change lube oil,
see 6.1.1. + 6.1.2.
Change oil filter cartridge,
see 6.1.3.
Change fuel filter cartridge,
see 6.2.1.
Check V-belts and retension as necessary,
see 6.5.
Check engine for leaks
Check engine mounts, retighten if necessary,
see 9.2.
Check valve clearance, adjust if necessary,
see 5.1. + 6.6.1.