Engine Operation 3.1 Commissioning
3.1.3 Other Preparations
● Check battery and cable connectors,
see 6.7.1.
● Transport hooks
Remove if fitted (see 6.7.3)
● Trial run
After engine has been prepared, let it run for
about 10 minutes without being loaded.
During and after trial run
- Check engine for leaks.
After engine has been turned off
- Check oil level,
see 6.1.2.
Top up with oil, if necessary,
see 3.1.1.
- Retension V-belt,
see 6.5).
3.1.4 Additional Maintenance Work
When commissioning new and reconditioned en-
gines, the following additional maintenance work
must be carried out:
● Change lube oil,
see 6.1.1. + 6.1.2.
● Change oil filter cartridge,
see 6.1.3.
● Change fuel filter cartridge,
see 6.2.1.
● Check V-belts and retension as necessary,
see 6.5.
● Check engine for leaks
● Check engine mounts, retighten if necessary,
see 9.2.
● Check valve clearance, adjust if necessary,
see 5.1. + 6.6.1.